Davey Coach — Install Checklist
GenTeks · Colorado · Signed 2026-03-31
ChuckFull install — all days
AustinFull install — all days
ReeceFri & Sat only
RussellOn-site staff — can add tasks
RonOn-site staff — can add tasks
📅 FRIDAY SCHEDULE
2:00 PMArrive on-site
5:00 PMNetwork can go down
6–7 PMPlanned wrap-up
⚠ Do not cut network before 5 PM
Buildings
5
Total Tasks
67
Completed
0
Remaining
67
Progress
0%
Assignee:
Day:
🏢 Building 10/21 tasks
0%
Clean up and label all keystones
Corner computer — make data drops consistent
Run second cable to Josh's desk
Tone and test all existing cable runs
Clean up and dress all cable runs in rack
Install 42U 4-post rack
Mount 2× 48-port full PoE switches in rack
Mount 4× 24-port patch panels in rack
Mount Rack UPS
Install shelf for NAS
Install 5-port flex switch — CFO office
Install 2× 8-port switches — cubicles downstairs
Install 1× 8-port switch — conference room
Install 1× 8-port switch — Nathan Patterson desk
Mount and configure 2× U6 Pro Access Points
Configure UDM Pro
Configure VLANs
Configure site-to-site VPN
Set up IT staff management access to UniFi
P2PInstall P2P link — Building 1 → Building 4
P2PInstall P2P link — Building 1 → Building 5
🏢 Building 20/11 tasks
0%
Move networking and cables outside the office
Use 16-port flex from Building 3 for cubicle area
Run 1 cable in back office
Tone and test all cable runs
Label all keystones and patch panel ports
Install 6U locking rack
Mount switch(es) in rack
Mount 2× 24-port patch panels
Install switch ears on existing switch
Install 2-port face plates
Mount and configure 1× Access Point
🏢 Building 30/13 tasks
0%
Install 1 cable at printer location
Install 2 cables at double desk area
Re-terminate current patch panel
Change all keystone colors to blue
Tone and test all cable runs
Label all keystones and patch panel ports
Install 6U locking rack
Mount 16-port switch in rack
Mount 24-port patch panel in rack
Install 2-port face plates
Install 4-port face plates
Replace AP — mount and configure new unit
Confirm camera relocation — Building 3 → Building 2
🏢 Building 40/8 tasks
0%
Replace 3 keystones to blue — Rio station section
Tone and test cable runs at Rio station
Label all keystones and patch panel ports
Mount AP to ceiling
Install shelf for UPS
Verify switch connectivity and port labeling
P2PInstall and aim P2P radio — Building 4 side (link to Building 1)
P2PConfirm P2P link is live and stable
🏢 Building 50/14 tasks
0%
Replace all keystone colors
Tone and test all cable runs
Label all keystones and patch panel ports
Clean up and dress all cable runs
Install 12U locking rack behind current rack
Move 4-post rack to Building 1
Mount switch(es) in new rack
Install shelf for UPS
Replace patch cables with blue patch cables
Replace patch cables with white patch cables
Move AP to ceiling wall mount
Configure AP
P2PInstall and aim P2P radio — Building 5 side (link to Building 1)
P2PConfirm P2P link is live and stable
Davey Coach Network Standardization · GenTeksSigned by Russell Henry · 2026-03-31